[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1021487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1021487,749,1,"单选题","在下列情形中，不能起吊的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","起重机装有音响清晰的喇叭、电铃信号装置，在起重臂、吊钩、平衡重等转动体上标有鲜明的色彩标志",false,{"key":16,"text":17,"correct":14},"B","起吊载荷达到起重机额定载荷的90％时，应先将重物吊离地面200～300 mm后，检查起重机的安全性、吊索的可靠性、重物的平稳性、绑扎的牢固性，确认后起吊",{"key":19,"text":20,"correct":21},"C","对关键、重要的货物，为防止吊装绳脱钩，应派人系好安全带、抓牢吊钩随重物一道安全吊至工位",true,{"key":23,"text":24,"correct":14},"D","吊运小口径钢管，按标记绑扎位置起吊，吊索与钢管的夹角为50°","有下述情况时，司机不应操作：起重机结构或零部件(如吊钩、钢丝绳、制动器、安全防护装置等)有影响安全工作的缺陷和损伤；吊物超载或有超载可能，吊物质量不清；吊物被埋置或冻结在地下、被其他物体挤压；吊物捆绑不牢，或吊挂不稳，被吊重物棱角与吊索之间未加衬垫；被吊物上有人或浮置物；作业场地昏暗，看不清场地、吊物情况或指挥信号。在操作中不得歪拉斜吊。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-其他安全","建筑工程",0]