[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1019359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1019359,744,1,"单选题","现代化高速线材一体化连续生产线的工艺设备流程，排序正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","加热炉→精轧机→预精轧→粗中扎→减定径→吐丝机→风冷线",false,{"key":16,"text":17,"correct":14},"B","加热炉→精轧机→预精轧→粗中扎→吐丝机→减定径→风冷线",{"key":19,"text":20,"correct":21},"C","加热炉→粗中扎→预精轧→精轧机→减定径→吐丝机→风冷线",true,{"key":23,"text":24,"correct":14},"D","加热炉→粗中扎→预精轧→精轧机→吐丝机→减定径→风冷线","高速线材一体化连续生产线的工艺设备流程：加热炉→粗中扎→预精轧→精轧机→减定径→吐丝机→风冷线。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-金属冶炼安全","建筑工程",0]