[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1019232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1019232,744,1,"单选题","根据《焦化安全规程》(GB12710)的规定，下列关于干熄焦起重机安全作业控制措施，说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应采用可靠的制动装置",false,{"key":16,"text":17,"correct":14},"B","应设置限位和位置检测装置",{"key":19,"text":20,"correct":14},"C","应设置速度检测装置",{"key":22,"text":23,"correct":24},"D","风速大于12 m／s时，起重机应停止作业",true,"干熄焦装置最高处，应设置风向仪和风速计。风速大于20 m／s时，起重机应停止作业。起重机轨道两端应设置固定装置。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-金属冶炼安全","建筑工程",0]