[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1017291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1017291,742,1,"单选题","尾矿库滩顶高程的检测，应沿坝（滩）顶方向布置测点进行实测，当滩顶高低相同时，应选较低处不少于（ ）个点。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","1",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","5","尾矿库滩顶标高的检测，应沿坝（滩）顶方向布置测点进行实测，其测量误差应小于20 mm。当滩顶一端高一端低时，应在低标高段选较低处检测1一3个点；当滩顶高低相间时，应选较低处不少于3个点；其他情况每100m坝长选较低处检测1一2个点，但总数不少于3个点。各测点中的最低点作为尾矿库滩顶标高。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-金属非金属矿山安全","建筑工程",0]