[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1016986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1016986,742,1,"单选题","排土场平台平整时，排土线整体均衡推进，坡顶线是直线形或弧形，排土场面向坡顶线方向有( )的反坡。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2％～5％",true,{"key":16,"text":17,"correct":18},"B","3％～6％",false,{"key":20,"text":21,"correct":18},"C","4％～7％",{"key":23,"text":24,"correct":18},"D","5％～8％","(1)山坡排土场周围，修筑可靠的截洪和排水设施拦截山坡汇水。 (2)排土场内平台设置2％～5％的反坡，并在排土场平台上修筑排水沟，以拦截平台表面及坡面汇水。 (3)当排土场范围内有出水点时，应在排土之前采取措施将水疏出；排土场底层排弃大块岩石，以便形成渗流通道。 (4)汛期前，疏通排土场内外截洪沟，详细检查排洪系统的安全情况，．备足抗洪抢险所需物资，落实应急救援措施。 (5)汛期及时了解和掌握水情和气象预报情况，并对排土场，下游泥石拦挡坝，通信、供电及照明线路进行巡视，发现问题应及时修复。 (6)洪水过后，对坝体和排洪构筑物进行全面认真的检查与清理。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-金属非金属矿山安全","建筑工程",0]