[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1016940":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1016940,742,1,"单选题","尾矿库建设项目包括新建、改建、( )以及回采、闭库的尾矿库建设工程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","扩建",true,{"key":16,"text":17,"correct":18},"B","勘察",false,{"key":20,"text":21,"correct":18},"C","巡查",{"key":23,"text":24,"correct":18},"D","检查","《尾矿库安全监督管理规定》中第九条，尾矿库建设项目包括新建、改建、扩建以及回采、闭库的尾矿库建设工程。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-金属非金属矿山安全","建筑工程",0]