[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140592":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},140592,74,2,"多选题","企业运用PDCA循环实施全面质量管理时，在处理阶段需要完成的步骤有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分析现状，找出存在的主要质量问题",false,{"key":16,"text":17,"correct":14},"B","执行计划",{"key":19,"text":20,"correct":21},"C","总结经验教训，制定相应标准、制度和规定",true,{"key":23,"text":24,"correct":21},"D","把未解决或新出现的问题转入下一轮PDCA循环",{"key":26,"text":27,"correct":14},"E","检查计划执行结果","CD","",{"id":6,"name":31,"category":32,"favorite":33},"(高级) 工商管理","经济金融",0]