[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-140009":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},140009,74,1,"单选题","下列关于项目组合评估的项目地图法的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","珍珠型项目具有较高的预期收益，但成功概率低",false,{"key":16,"text":17,"correct":18},"B","面包和黄油项目开发成功率高，但预期收益不是很好",true,{"key":20,"text":21,"correct":14},"C","白象型项目预期收益不好，成功概率高",{"key":23,"text":24,"correct":14},"D","牡蛎型项目潜在收益高，而且开发成功率高","本题考查的是项目地图法。B选项正确；珍珠型项目具有较高的预期收益和很高的成功概率，故A错误；白象项目通常不仅风险较大，预期效益好，故C错误；牡蛎型项目潜在收益很高，但是技术开发成功的可能性较低，故D错误。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]