[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-139834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},139834,74,1,"单选题","关于PDCA循环的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","推动PDCA循环，关键在C阶段",true,{"key":16,"text":17,"correct":18},"B","PDCA循环将工作过程分为计划、执行、检查、处理四个阶段",false,{"key":20,"text":21,"correct":18},"C","PDCA循环作为企业开展质量改进活动的一般方法，适用于企业的各方面工作",{"key":23,"text":24,"correct":18},"D","质量改进是质量管理PDCA循环中的一个必要环节或阶段，是PDCA循环螺旋式上升的基础","本题考查实施全面质量管理的基本方法。选项A错误，推动PDCA循环，关键在A阶段。参见教材P133-134。掌握“全面质量管理和六西格玛管理”知识点。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]