[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-139761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},139761,74,1,"单选题","某企业为零件转向节进行单对象流水线的组织设计，日生产量为60件，每日工作8小时，时间利用系数为0.95，废品率为1%，该转向节的平均节拍是（ ）分\u002F件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5.0",false,{"key":16,"text":17,"correct":14},"B","5.5",{"key":19,"text":20,"correct":14},"C","6.5",{"key":22,"text":23,"correct":24},"D","7.5",true,"节拍是指流水线生产上连续生产两个相同制品的间隔时间。流水线的平均节拍的计算公式为： 。式中，r为流水线的平均节拍；Te为计划期流水线的有效工作时间；T0为计划期流水线的制度工作时间；β为工作时间有效利用系数；Q为计划期的产品产量。将数据代入得：Te＝βT0＝0.95×8×60＝456（分）；Q＝60\u002F0.99＝60.6（件）；r＝Te\u002FQ＝456\u002F60.6＝7.5（分\u002F件）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]