[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-139739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},139739,74,1,"单选题","某企业采用平行顺序移动方式对一种零件进行加工，该零件投资批量为6件，有4道加工工序：按照加工顺序，单件每道工序作业时间依次为20分钟、10分钟、25分钟、15分钟，假设零件移动用时为零。将一个批次的该零件全部生产出来所需要的时间为（ ）分钟。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","120",false,{"key":16,"text":17,"correct":14},"B","200",{"key":19,"text":20,"correct":21},"C","245",true,{"key":23,"text":24,"correct":14},"D","300","平行顺序移动方式下，零件全部生产完成的生产周期可按以下公式计算： 由题意，将一个批次的该零件全部生产出来所需要的时间为：T＝6×（20＋10＋25＋15）－5×（10＋10＋15）＝245（分钟）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]