[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-139730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},139730,74,1,"单选题","某企业为所生产的零件转向节进行单对象流水线的组织设计，计划日生产量为60件，每日工作8小时，时间有效利用系数为0.95,预计废品率为 1%，该转向节的平均节拍为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6.5",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7.5",true,{"key":23,"text":24,"correct":14},"D","7","本题考查的是节拍的计算。流水线的平均节拍=（工作时间有效利用系数×计划期流水线的制度工作时间）\u002F计划期的产品产量，计算如下： （1）工作时间有效利用系数：0.95 （2）计划期流水线工作时间：8×60=480分钟 （3）计划期的产品产量：60×（1+1%）=60.6件 （4）流水线的平均节拍=（0.95×480）\u002F60.6≈7.5分钟\u002F件，故选C",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]