[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-139637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},139637,74,1,"单选题","某企业为所生产的零件转向节进行单对象流水线的组织设计，计划日生产量为80件，每日工作8小时，时间有效利用系数为0.90,预计废品率为 1%，该转向节的平均节拍为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5.0",false,{"key":16,"text":17,"correct":18},"B","5.3",true,{"key":20,"text":21,"correct":14},"C","5.5",{"key":23,"text":24,"correct":14},"D","6.0","节拍是指流水线生产上连续生产两个相同制品的间隔时间。流水线的平均节拍的计算公式为：式中，r为流水线的平均节拍；T为计划期流水线的有效工作时间；T为计划期流水线的制度工作时间；β为工作时间有效利用系数，Q为计划期的产品产量（包括计划产量和预计废品率）。将数据代入得：T＝βT＝0.90×8×60＝432（分）；Q＝80÷0.99＝80.8（件）；r＝T\u002FQ＝432÷80.8≈5.3（分／件）。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 工商管理","经济金融",0]