[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014641":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1014641,739,2,"多选题","PBA工法桩柱梁体系施工时，扣拱和小导洞拱部开挖前，可以选择辅助工法，如（ ），保证开挖及支护安全。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","小导管注浆超前加固地层",true,{"key":16,"text":17,"correct":14},"B","弧形开挖导坑",{"key":19,"text":20,"correct":14},"C","留核心土",{"key":22,"text":23,"correct":24},"D","土钉支护",false,{"key":26,"text":27,"correct":14},"E","及时喷射混凝土","ABCE","本题考查的是暗挖法施工。扣拱和小导洞拱部开挖前，可以选择辅助工法，如小导管注浆超前加固地层，弧形开挖导坑、留核心土，架设临时支撑、及时喷射混凝土等措施，保证开挖及支护安全。",{"id":6,"name":31,"category":32,"favorite":33},"安全实务-建筑施工安全","建筑工程",0]