[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014418":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1014418,739,1,"单选题","关于盾构法施工的联络通道施工，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","联络通道施工包括联络通道和废水泵房施工两部分，一般是采用人工开挖",false,{"key":16,"text":17,"correct":18},"B","可开挖较长的隧道",true,{"key":20,"text":21,"correct":14},"C","若遇局部透水砂层有涌水情况发生，须立即喷射掺有大量速凝剂的混凝土封闭涌水面",{"key":23,"text":24,"correct":14},"D","在施工作业期间需加强排水，以防士体长时间霞泡变软而发生坍塌引发恶性事故","本题考查的是城市轨道交通施工工程施工主要安全技术。选项B说法错误，联络通道施工包括联络通道和废水泵房施工两部分，一般是采用人工开挖，与矿山法施工相似，但开挖的隧道长度较短。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]