[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014408,739,1,"单选题","中洞法暗挖地铁车站顶拱施工时，顶芯梁的混凝土达到强度要求后，中洞拱顶施工前，分段拆除顶部中隔墙，通常分段拆除长度为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8m",false,{"key":16,"text":17,"correct":14},"B","12m",{"key":19,"text":20,"correct":21},"C","18m",true,{"key":23,"text":24,"correct":14},"D","24m","本题考查的是暗挖法施工。顶芯梁的混凝土达到强度要求后，中洞拱顶施工前，分段拆除顶部中隔墙，通常分段拆除长度为18m。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]