[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1014405,739,1,"单选题","PBA工法桩柱梁体系施工时，多个小导洞开挖时，进行工况分析，合理开挖顺序，先施工（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两侧下导洞",false,{"key":16,"text":17,"correct":18},"B","两侧上导洞",true,{"key":20,"text":21,"correct":14},"C","中部下导洞",{"key":23,"text":24,"correct":14},"D","中部上导洞","本题考查的是暗挖法施工的主要关键技术。多个小导洞开挖时，进行工况分析，合理开挖顺序，先施工两侧上导洞，拉开一定距离后，再施工中部下导洞，最后施工中部上导洞，相邻导洞之间错开一定距离施工，减少围岩扰动次数，减小群洞效应，以策安全。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]