[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014402":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1014402,739,1,"单选题","PBA工法扣拱施工的安全技术难点不包含（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大跨度暗挖施工风险高、造价高",true,{"key":16,"text":17,"correct":18},"B","扣拱施工结构受力复杂",false,{"key":20,"text":21,"correct":18},"C","初支和二衬的施工节点多",{"key":23,"text":24,"correct":18},"D","施工作业面狭小，施工组织困难","本题考查的是暗挖法施工的主要关键技术。选项A中，造价高不属于技术难点。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]