[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014400":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014400,739,1,"单选题","PBA工法的施工流程：①桩、柱顶梁施工；②钢管柱吊装及灌注混凝土；③导洞开挖；④顶部初支及二衬扣拱；⑤边桩施工、柱孔开挖；⑥站厅层施工；⑦底梁施工；⑧站台层施工，正确的顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①④⑥⑧③⑤⑦②",false,{"key":16,"text":17,"correct":14},"B","⑦②①③⑤④⑥⑧",{"key":19,"text":20,"correct":21},"C","③⑤⑦②①④⑥⑧",true,{"key":23,"text":24,"correct":14},"D","⑥⑧③⑤⑦②①④","本题考查的是暗挖法施工的主要关键技术。具体施工流程如下：导洞开挖→边桩施工、柱孔开挖→底梁施工→钢管柱吊装及灌注混凝土→桩、柱顶梁施工→顶部初支及二衬扣拱→站厅层施工→站台层施工。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]