[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1014371,739,1,"单选题","城市轨道交通地下工程建设应采取经济、可行、主动的处置措施来减少或降低风险，风险控制必须坚持（ ）的原则。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","“安全第一、保护环境、预防为主”",true,{"key":16,"text":17,"correct":18},"B","“安全第一、预防为主、综合治理”",false,{"key":20,"text":21,"correct":18},"C","“同时设计、同时施工、同时投产使用”",{"key":23,"text":24,"correct":18},"D","“法人是企业安全生产第一责任人”","城市轨道交通地下工程建设风险控制必须坚持“安全第一、保护环境、预防为主”的原则，采取经济、可行、主动的处置措施来减少或降低风险。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]