[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014344,739,1,"单选题","搭设高度超过规范要求的脚手架应编制专项施工方案，基础、连墙件应经设计计算。专项施工方案必须经专家论证的，必须采取加强措施。专项施工方案必须经专家论证的情况包括搭设高度至少超过（ ）的架体。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10m",false,{"key":16,"text":17,"correct":14},"B","30m",{"key":19,"text":20,"correct":21},"C","50m",true,{"key":23,"text":24,"correct":14},"D","100m","搭设高度超过规范要求的脚手架应编制专项施工方案，基础、连墙件应经设计计算；搭设高度超过50m的架体，必须采取加强措施，专项施工方案必须经专家论证。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]