[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014265":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014265,739,1,"单选题","脚手架工程必须有完善的施工方案，并经企业技术负责人审批。并且有完善的安全防护措施，要按规定设置安全网、防护栏、挡脚板。下列关于脚手架工程的安全技术要求中，说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","操作人员上下架子，要有保证安全的扶梯、爬梯或斜道",false,{"key":16,"text":17,"correct":14},"B","必须有良好的防电、避雷装置，钢脚手架等均应可靠接地，高于四周建筑物的脚手架应设避雷装置",{"key":19,"text":20,"correct":21},"C","脚手板要铺满、铺稳，应保留探头板，并要保证有3个支撑点，并绑扎牢固",true,{"key":23,"text":24,"correct":14},"D","遇6级以上大风或大雾、大雨，应暂停高处作业，雨雪后上架操作要有防滑措施","脚手板要铺满、铺稳，不得留探头板，要保证有3个支撑点，并绑扎牢固。在脚手架上同时进行多层作业的情况下，各作业层之间应设置可靠的防护棚，以防止上层坠物伤及下层作业人员。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]