[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014229,739,1,"单选题","开挖深度大于等于（ ）或开挖深度小于（ ）但现场地质情况和周围环境较复杂的基坑工程及其他需要检测的基坑工程应实施基坑工程监测。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2m，2m",false,{"key":16,"text":17,"correct":14},"B","3m，3m",{"key":19,"text":20,"correct":21},"C","5m，5m",true,{"key":23,"text":24,"correct":14},"D","8m，8m","本题考查的是基坑施工作业要求。开挖深度大于等于5m或开挖深度小于5m但现场地质情况和周围环境较复杂的基坑工程及其他需要检测的基坑工程应实施基坑工程监测。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]