[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1014177":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1014177,739,1,"单选题","采用复合土钉支护的基坑开挖施工，基坑开挖应与土钉施工分层交替进行，应缩短无支护暴露时间。采用分层方法进行土方开挖，每层土方开挖的底标高应低于相应土钉位置，且距离不宜大于200mm，每层分段长度不应大于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10m",false,{"key":16,"text":17,"correct":14},"B","20m",{"key":19,"text":20,"correct":21},"C","30m",true,{"key":23,"text":24,"correct":14},"D","40m","应采用分层方法进行土方开挖，每层土方开挖的底标高应低于相应土钉位置，且距离不宜大于200mm，每层分段长度不应大于30m。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]