[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1013971,739,1,"单选题","建设项目电器设备容量小，施工周期短时，可以采用的施工现场供电形式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","独立变配电所供电",false,{"key":16,"text":17,"correct":14},"B","自备变压器供电",{"key":19,"text":20,"correct":14},"C","电压220V\u002F380V供电",{"key":22,"text":23,"correct":24},"D","借用电源",true,"本题考查的是施工现场供电形式。施工现场的供电形式包括：（1）独立变配电所供电。一些较大的项目（规划小区、新建学校、新建工厂等），可利用配套建设的变配电所供电。避免了重复投资，且使用规范。（2）自备变压器供电。城市中高压输电的电压一般为10kV，通常用电设备的额定电压一般为220V\u002F380V。可利用附近高压电网，增设变压器等配套设备供电。（3）电压220V\u002F380V供电。对于电气设备容量较小的项目，在附近220V\u002F380V电源余量允许的情况下，到有关部门申请直接供电。（4）借用电源。建设项目电器设备容量小，施工周期短，可在有关部门申请就近借用电源。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]