[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013759":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013759,739,1,"单选题","装载机作业前，应先（ ），检查各部是否完好，确认一切正常后，再开始装载作业。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","无负荷运转3～5min",true,{"key":16,"text":17,"correct":18},"B","满负荷运转3～5min",false,{"key":20,"text":21,"correct":18},"C","无负荷运转10min",{"key":23,"text":24,"correct":18},"D","满负荷运转10min","本题考查的是常用土石方机械的安全技术要求。装载机应先无负荷运转3～5min，检查各部是否完好，确认一切正常后，再开始装载作业。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]