[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1013579,739,1,"单选题","不符合施工组织设计编制原则的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","符合施工合同或招标文件中有关工程进度、质量、安全、环境保护、造价等方面的要求",false,{"key":16,"text":17,"correct":18},"B","不使用新技术、新工艺、新材料和新设备",true,{"key":20,"text":21,"correct":14},"C","坚持科学的施工程序和合理的施工顺序，采取季节性施工措施",{"key":23,"text":24,"correct":14},"D","采取技术和管理措施，推广建筑节能和绿色施工","积极开发，使用新技术和新工艺，推广应用新材料和新设备是编制施工组织设计的原则之一，故B选项表述错误。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]