[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013539,739,1,"单选题","下列关于施工组织设计说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位工程施工组织设计是以单位（子单位）工程为对象编制的施工组织设计，由项目技术负责人审批",true,{"key":16,"text":17,"correct":18},"B","施工方案是以分部（分项）工程或专项工程为主要对象编制的施工技术与组织方案",false,{"key":20,"text":21,"correct":18},"C","施工组织设计的编制要与质量、环境和职业健康安全三个管理体系有效结合",{"key":23,"text":24,"correct":18},"D","施工组织设计编制时要依据工程施工合同或招标投标文件结合施工企业的生产能力、机具设备状况、技术水平等等情况进行编制","单位工程施工组织设计应由施工单位技术负责人或技术负责人授权的技术人员审批",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]