[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1013374,739,1,"单选题","下列关于钢管柱施工相关要求的说法中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","为便于起吊，钢管柱出厂前应在管顶焊接耳片，位置约在管顶下50mm",false,{"key":16,"text":17,"correct":14},"B","耳片侧面须加焊肋板，确保在最不利位置起吊时不致侧翻破坏",{"key":19,"text":20,"correct":21},"C","当钢管柱底部轴线对齐后，对其进行调直时，大的偏差靠兰花口调整，由吊臂进行细致调整",true,{"key":23,"text":24,"correct":14},"D","对比较长的钢管柱做有效临时支护，尽快脱钩后再继续进行焊接工序，加快吊装速度","当钢管柱底部轴线对齐后，对其进行调直时，可用2台经纬仪在两个垂直方向沿轴线向上观察管顶轴线，大的偏差靠吊臂调整，用4根钢丝绳拉住管顶，靠兰花口进行细致调整。调垂直后焊接应四周对称均匀进行。避免焊接收缩引起初支度改变。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]