[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1013372,739,1,"单选题","PBA工法就是在边导洞内施工车站的边桩，在中岛洞内施工梁柱，然后在桩柱体系间进行初支和二衬扣拱，形成车站的顶部结构，并在顶部结构的保护下由上至下逆筑车站结构。PBA法具体施工流程为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","边桩施工、柱孔开挖→导洞开挖→桩、柱顶梁施工→钢管柱吊装及灌注混凝土→底梁施工→顶部初支及二衬扣拱→站厅层施工→站台层施工",false,{"key":16,"text":17,"correct":14},"B","边桩施工、柱孔开挖→底梁施工→导洞开挖→钢管柱吊装及灌注混凝土→桩、柱顶梁施工→顶部初支及二衬扣拱→站厅层施工→站台层施工",{"key":19,"text":20,"correct":14},"C","导洞开挖→边桩施工、柱孔开挖→桩、柱顶梁施工→顶部初支及二衬扣拱→底梁施工→钢管柱吊装及灌注混凝土→站厅层施工→站台层施工",{"key":22,"text":23,"correct":24},"D","导洞开挖→边桩施工、柱孔开挖→底梁施工→钢管柱吊装及灌注混凝土→桩、柱顶梁施工→顶部初支及二衬扣拱→站厅层施工v站台层施工",true,"PBA工法具体施工流程如下：导洞开挖→边桩施工、柱孔开挖→底梁施工→钢管柱吊装及灌注混凝土→桩、柱顶梁施工→顶部初支及二衬扣拱→站厅层施工→站台层施工。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]