[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1013368,739,1,"单选题","暗挖车站常用施工方法包括PBA法、CRD法、双侧壁导坑法、中洞法、侧洞法、柱洞法等施工方法。施工中先开挖中间部分，在中洞内施作梁、柱结构，然后再开挖两侧部分，并逐渐将侧洞顶部荷载通过中洞初期支护转移到梁、柱结构上的施工方法，属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","PBA法",false,{"key":16,"text":17,"correct":14},"B","CRD法",{"key":19,"text":20,"correct":21},"C","中洞法",true,{"key":23,"text":24,"correct":14},"D","侧洞法","中洞法施工就是先开挖中间部分，在中洞内施作梁、柱结构，然后再开挖两侧部分，并逐渐将侧洞顶部荷载通过中洞初期支护转移到梁、柱结构上。中洞法施工工序复杂，但两侧对称施工，比较容易解决侧压力从中洞转移到梁柱上时产生的不平衡侧压力问题，施工引起的地表下沉交易控制。该方法在无水、地层相对较好时应用。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]