[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013366":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1013366,739,1,"单选题","下列不属于暗挖车站工法选择原则的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全可行性原则",false,{"key":16,"text":17,"correct":14},"B","工期可控性原则",{"key":19,"text":20,"correct":21},"C","整体可靠性原则",true,{"key":23,"text":24,"correct":14},"D","经济合理性原则","暗挖车站工法选择原则： (1)安全可行性原则。首先必须从施工安全的角度出发，选取可靠的施工工法。同时选取时必须考虑周围环境安全，保证将地面沉降控制在允许范围内。 (2)工期可控性原则。采用施工条件好、机械化程度高的工法开挖暗挖车站，减少或避免施工中可能遇到的各种困难和障碍。 (3)经济合理性原则。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]