[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1013334,739,1,"单选题","现浇柱模板拆除顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","拆除斜撑或拉杆(或钢拉条)→拆除竖楞→自上而下拆除柱箍或横楞",false,{"key":16,"text":17,"correct":14},"B","自上而下拆除柱箍或横楞→拆除斜撑或拉杆(或钢拉条)→拆除竖楞",{"key":19,"text":20,"correct":14},"C","自上而下拆除柱箍或横楞→拆除竖楞→拆除斜撑或拉杆(或钢拉条)",{"key":22,"text":23,"correct":24},"D","拆除斜撑或拉杆(或钢拉条)→自上而下拆除柱箍或横楞→拆除竖楞",true,"现浇柱模板拆除顺序是，拆除斜撑或拉杆(或钢拉条)→自上而下拆除柱箍或横楞→拆除竖楞并由上而下拆除模板连接件、模板面。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]