[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013332,739,1,"单选题","一般现浇楼盖及框架结构的拆模顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拆柱模斜撑与柱箍→拆柱侧模→拆楼板底模→拆梁侧模→拆梁底模",true,{"key":16,"text":17,"correct":18},"B","拆梁底模→拆梁侧模→拆楼板底模→拆柱侧模→拆柱模斜撑与柱箍",false,{"key":20,"text":21,"correct":18},"C","拆柱侧模→拆柱模斜撑与柱箍→拆梁底模→拆梁侧模→拆楼板底模",{"key":23,"text":24,"correct":18},"D","拆楼板底模→拆梁底模→拆柱模斜撑与柱箍→拆梁侧模→拆柱侧模","一般现浇楼盖及框架结构的拆模顺序是，拆柱模斜撑与柱箍→拆柱侧模→拆楼板底模→拆梁侧模→拆梁底模。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]