[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1013330,739,1,"单选题","拆模时混凝土强度必须符合要求，下列关于模板拆除的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不承重的侧模板，应根据与结构同条件养护试块强度达到规定，方可拆除",false,{"key":16,"text":17,"correct":14},"B","一般墙体大模板在常温条件下，只要混凝土强度能保证其表面及棱角不因拆除模板而受损坏，即可拆除",{"key":19,"text":20,"correct":14},"C","承重模板。混凝土强度达到1N／mm2即可拆除",{"key":22,"text":23,"correct":24},"D","在拆模过程中，实际结构混凝土强度并未达到要求，应暂停拆模",true,"拆模时混凝土强度： (1)不承重的侧模板，包括梁、柱、墙的侧模板，只要混凝土强度能保证其表面及棱角不因拆除模板而受损坏，即可拆除。 (2)一般墙体大模板在常温条件下，混凝土强度达到1 N／mm2即可拆除。 (3)承重模板，包括梁、板等水平结构构件底模，应根据与结构同条件养护试块强度达到规定，方可拆除。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]