[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013182":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013182,739,1,"单选题","脚手架搭设应选择合理的搭设顺序和施工操作程序，这是保证脚手架搭设安全和减少架体搭设积累误差的重要举措，脚手架搭设应按顺序施工。下列不符合规定的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","落地作业脚手架、悬挑脚手架一次搭设高度不应超过最上层连墙件三步，且自由高度不应大于6m",true,{"key":16,"text":17,"correct":18},"B","支撑脚手架应逐排、逐层进行搭设",false,{"key":20,"text":21,"correct":18},"C","剪刀撑、斜撑杆等加固杆件应随架体同步搭设，不得滞后安装",{"key":23,"text":24,"correct":18},"D","构建组装类脚手架的搭设应自下而上按步架设，并逐层改变搭设方向","落地作业脚手架、悬挑脚手架一次搭设高度不应超过最上层连墙件两步，且自由高度不应大于4 m。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]