[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013152,739,1,"单选题","支护的作业应按支护结构设计规定的施工顺序和开挖深度分层开挖。下列关于支护作业的要求中，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当支护结构构件强度接近开挖阶段设计强度时，方可向下开挖",true,{"key":16,"text":17,"correct":18},"B","对土钉墙，应在土钉.喷射混凝土面层的养护时间大于2天后，方可开挖下层土方",false,{"key":20,"text":21,"correct":18},"C","开挖至锚杆.土钉施工作业面时，开挖面与锚杆.土钉的高差不宜大于500mm",{"key":23,"text":24,"correct":18},"D","采用锚杆或支撑的支护结构，在未达到设计规定的拆除条件时，严禁拆除锚杆或支撑","本题考查的是基坑施工作业要求。当支护结构构件强度达到开挖阶段设计强度时，方可向下开挖。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]