[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013127":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013127,739,1,"单选题","基坑开挖过程中，一旦出现了渗水或漏水，应根据水量大小，采用坑底设沟排水、引流修补、密实混凝土封堵、压密注浆、高压喷射注浆等方法及时进行处理。如果水泥土墙等重力式支护结构位移超过设计估计值，应做好监测，掌握发展趋势。若持续发展，则应采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水泥土墙背后卸载、加快垫层施工及加大垫层厚度和架设支撑等方法及时处理",true,{"key":16,"text":17,"correct":18},"B","架设支撑或锚杆、支护墙背卸土等方法及时进行处理",false,{"key":20,"text":21,"correct":18},"C","及时浇筑垫层，必要时可以加厚垫层，形成下部水平支撑",{"key":23,"text":24,"correct":18},"D","设坑外回灌井、进行坑底加固、垫层随挖随浇、加厚垫层或采用配筋垫层、设置坑底支撑等方法及时进行处理","如果水泥土墙等重力式支护结构位移超过设计估计值，应做好监测，掌握发展趋势。若持续发展，则应采用水泥土墙背后卸载、加快垫层施工及加大垫层厚度和架设支撑等方法及时处理。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]