[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1013101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1013101,739,1,"单选题","下列关于施工安全作业的要求中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在挖土机工作范围内，不允许进行其他作业",true,{"key":16,"text":17,"correct":18},"B","除基坑支护设计要求允许外，基坑边10m范围内不得堆土、推料、放置机具",false,{"key":20,"text":21,"correct":18},"C","多台机械开挖．挖土机间距应大于1m",{"key":23,"text":24,"correct":18},"D","逆作法挖土应由下而上，先挖坡脚。逐层进行","基坑周边、放坡平台的施工荷载应按照设计要求进行控制；基坑开挖的土方不应在临近建筑及基坑周边影响范围内堆放，并应及时外运。除基坑支护设计要求允许外，基坑边1 m范围内不得堆土、推料、放置机具。基坑开挖时，两人操作间距应大于2．5 m。多台机械开挖，挖土机间距应大于10m。在挖土机工作范围内，不允许进行其他作业。挖土应由上而下，逐层进行，严禁先挖坡脚或逆坡挖土。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]