[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1012982":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1012982,739,1,"单选题","下列关于临时用电施工组织设计的要求中，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","临时用电工程图纸应与主体工程图纸一同绘制，临时用电工程应按图施工",true,{"key":16,"text":17,"correct":18},"B","临时用电施工组织设计及变更必须履行“编制、审核、批准”程序",false,{"key":20,"text":21,"correct":18},"C","临时用电工程必须经编制、审核、批准部门和使用单位共同验收，合格后方可投入使用",{"key":23,"text":24,"correct":18},"D","对于小型工地(现场临时用电设备5台以下或者设备总容量在50 kW以下)，可不编制临时用电施工组织设计，但仍要编制安全用电措施和电器防火措施，并且履行“编制、审核、批准、验收”的管理程序","临时用电工程图纸应单独绘制，临时用电工程应按图施工。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]