[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1012939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1012939,739,1,"单选题","建设项目电气设备容量小，施工周期时间短，可采取就近借用电源的方法，解决施工现场的临时用电，此供电形式为（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","独立变配电所供电",false,{"key":16,"text":17,"correct":14},"B","自备变压器供电",{"key":19,"text":20,"correct":14},"C","低压220\u002F380V供电",{"key":22,"text":23,"correct":24},"D","接用电源",true,"借用电源。若建设项目电气设备容量小，施工周期时间短，可采取就近借用电源的方法，解决施工现场的临时用电，如借用就近原有变压器供电或借用附近单位电源供电，但须征得有关部门批准同意。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]