[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1012881":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1012881,739,1,"单选题","塔式起重机的安装流程中包含：①安装塔身；②基础的制作与安装；③安装起重臂；④安装回转支撑等步骤。以上步骤中，按照塔式起重机的安装流程要求进行排序，排在第二步的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①",true,{"key":16,"text":17,"correct":18},"B","②",false,{"key":20,"text":21,"correct":18},"C","③",{"key":23,"text":24,"correct":18},"D","④","本题考查的是起重机械安全技术。塔式起重机的安装流程：①基础的制作与安装；②安装塔身；③安装顶升套架；④安装回转支撑；⑤安装塔司节和司机室；⑥安装平衡臂；⑦安装塔尖；⑧安装起重臂；⑨安装钢丝绳和电器装置；⑩调试。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]