[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1012852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1012852,739,1,"单选题","双笼不带对重升降机的安装过程中，首先应将基础表面清扫干净后安装底盘，然后安装1个基础节和安装2个标准节，而后应当安装的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将左右两只吊笼下的吊笼缓冲弹簧安装到位",true,{"key":16,"text":17,"correct":18},"B","安装左吊笼",false,{"key":20,"text":21,"correct":18},"C","安装右吊笼",{"key":23,"text":24,"correct":18},"D","安装吊笼传动机构","双笼不带对重升降机的安装程序： (1)将基础表面清扫干净后安装底盘，然后安装1个基础节和安装2个标准节，并将左右两只吊笼下的吊笼缓冲弹簧安装到位。 (2)安装吊笼：①用起重设备将左吊笼吊起就位，并安装左吊笼的传动小车。②将左笼的传动小车与左吊笼的连接耳板对好后，穿人传感器销轴，并将止动槽向上，装上固定板。将左笼的传动小车的制动器复位。③采用同样方法安装右吊笼并连接传动板。④安装左右吊笼的笼顶安全围栏。⑤继续安装标准节和附着至需要高度，紧固所有标准节螺栓。 (3)左右吊笼机电分别通电试运行。要求升降机启制动平稳，无异常声晋。 (4)安装调试。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]