[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1012846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1012846,739,1,"单选题","塔式起重机安装完成后需要进行顶升，下列关于顶升过程描述错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在顶升过程中不得随意拆卸液压元器件",false,{"key":16,"text":17,"correct":14},"B","在顶升起重臂的正下方准备好顶升用的标准节，并选择好配平重物",{"key":19,"text":20,"correct":21},"C","在顶升油缸的半程进行试运转",true,{"key":23,"text":24,"correct":14},"D","吊起配平重物，调整变幅小车的位置找到平衡点","在顶升油缸的全程进行试运转。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-建筑施工安全","建筑工程",0]