[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1006932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1006932,736,2,"多选题","单项工程中间交接的内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","按设计文件内容对工程实物量的核实",true,{"key":16,"text":17,"correct":14},"B","工程质量的初验资料及有关调试记录的审核验证",{"key":19,"text":20,"correct":14},"C","安装专用工具和剩余随机备件、材料的清点",{"key":22,"text":23,"correct":14},"D","尾项项目清单与实施方案的确认",{"key":25,"text":26,"correct":27},"E","按工程竣工验收报告进行验收",false,"ABCD","本题考查的是质量验收程序和组织。单项工程中间交接的内容：（1）按设计文件内容对工程实物量的核实。（2）工程质量的初验资料及有关调试记录的审核验证。（3）安装专用工具和剩余随机备件、材料的清点。（4）尾项项目清单与实施方案的确认。（5）随机技术资料完整性的核查。",{"id":6,"name":31,"category":32,"favorite":33},"安全实务-化工安全","建筑工程",0]