[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1006904":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1006904,736,2,"多选题","单项工程中间交接应具备的条件有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按设计文件内容施工完成",true,{"key":16,"text":17,"correct":14},"B","工程质量初验合格",{"key":19,"text":20,"correct":21},"C","安装施工临时设施已拆除，主体工程施工完成",false,{"key":23,"text":24,"correct":14},"D","现场满足安全管理规定的试车要求",{"key":26,"text":27,"correct":14},"E","未完工程尾项的责任已经确认，完成时间已经明确，且不影响联动试车","ABDE","本题考查的是质量验收程序和组织。选项C说法错误，应为：安装施工临时设施已拆除，竖向工程施工完成。",{"id":6,"name":31,"category":32,"favorite":33},"安全实务-化工安全","建筑工程",0]