[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1006827":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1006827,736,2,"多选题","对于新建生产装置或大修装置，一般分两次进行开工条件确认，即中间交接前进行“三查四定”和装置引料前进行开工条件检查，其中，“四定”指的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","定任务",true,{"key":16,"text":17,"correct":14},"B","定人员",{"key":19,"text":20,"correct":14},"C","定时间",{"key":22,"text":23,"correct":14},"D","定措施",{"key":25,"text":26,"correct":27},"E","定目标",false,"ABCD","本题考查的是化工装置开停工安全技术。“三查四定”，即查设计漏项、查工程质量及隐患、查未完工程量，定任务、定人员、定时间、定措施，限期完成。",{"id":6,"name":31,"category":32,"favorite":33},"安全实务-化工安全","建筑工程",0]