[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1005771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1005771,736,1,"单选题","关于安装工程的施工质量检验，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","隐蔽工程在隐蔽前应由施工单位报验，建设单位／监理单位组织验收，并形成验收文件",false,{"key":16,"text":17,"correct":18},"B","检验项目质量验收出现不合格项时，不得验收",true,{"key":20,"text":21,"correct":14},"C","检验项目质量验收出现不合格项时，不合格项处理后，经有资质的检测单位检测鉴定或原设计单位核算满足安全和使用功能的要求，可予以让步接收",{"key":23,"text":24,"correct":14},"D","检验项目质量验收出现不合格项时，不合格项经处理后仍不符合安全使用要求时，不得验收","本题考查的是施工过程质量检验。选项B说法错误，检验项目质量验收出现不合格项时，不合格项返工后应按规定重新进行质量验收。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-化工安全","建筑工程",0]