[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1005667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1005667,736,1,"单选题","跟踪HAZOP进行整改是不可避免的。在某些适当的阶段，应对项目进行进一步的审查，最好由原来的负责人负责进一步的审查工作。这种审查目标不包含（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确保所有的整改不损害原来的评估",false,{"key":16,"text":17,"correct":14},"B","审查资料，特别是制造商的数据",{"key":19,"text":20,"correct":14},"C","确保已经执行了所有提出的推荐措施",{"key":22,"text":23,"correct":24},"D","确保所有的成员知道并且对采取有关的措施形成一致意见",true,"本题考查的是工艺过程安全设计。这种审查有三个目标：（1）确保所有的整改不损害原来的评估。（2）审查资料，特别是制造商的数据。（3）确保已经执行了所有提出的推荐措施。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-化工安全","建筑工程",0]