[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1005662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1005662,736,1,"单选题","现场条件不允许进行管道液压和气压试验时，可同时采用无损检测、管道系统柔性分析和泄漏试验代替压力试验，但应经建设单位和设计单位同意。替代方法如下：所有环向、纵向对接焊缝和螺旋焊焊缝，应进行100%射线检测或（ ）；其余的所有焊缝，应进行100%的渗透检测或100%的磁粉检测。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100%的渗透检测",false,{"key":16,"text":17,"correct":14},"B","100%的磁粉检测",{"key":19,"text":20,"correct":21},"C","100%超声检测",true,{"key":23,"text":24,"correct":14},"D","100%的渗透检测和100%的磁粉检测","本题考查的是施工过程质量检验。现场条件不允许进行管道液压和气压试验时，可同时采用无损检测、管道系统柔性分析和泄漏试验代替压力试验，但应经建设单位和设计单位同意。替代方法如下：所有环向、纵向对接焊缝和螺旋焊焊缝，应进行100%射线检测或100%超声检测；其余的所有焊缝，应进行100%的渗透检测或100%的磁粉检测。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-化工安全","建筑工程",0]